)The Cogeneration plant operations will deliver steam to Natural Fuel Singapore’s Bio Diesel facilities and clean electricity to the customer. The facility is designed to use a combination of natural gas, bio diesel and waste products from Natural Fuel Singapore’s bio diesel plant. The use of renewable resources will contribute to higher energy efficiency at the plant

The plant will operate 24 hours per day 360 days per year, as follows

1. Operational life cycle of plant           15 years
2. Annual operating hours                    8640 hrs
3. Maximum electrical demand              5 MW
4. Annual export MWhr                         43,200 MWhr
5. Steam demand                                45 T per hr (plus 20% capability)
6. Annual steam demand                      388,800 T (plus 20% capacity)